Health, Safety, Environmental and C.E Machinery Directive Support
Constructus provided engineering plateau phase Heaalth, Safety, Environmental and C.E Mahinery directive support to Broetje Automation for their off to Airbus for a novel aircraft wing assembley plant.
Principal Contractor Advisor
Constructus established the site, prepared the construction phase Health & Safety plan for the construction phase of the implementaton of the project, including full time Health & Safety officer on site.
 
Wing Spar Production Facility

For Broetje Automation, Constructus provided the complete Health & Safety management for the construction of a production facility for the machining and assembly of the carbon fibre wing spars by GKN Aerospace for the Airbus A350 AWB aircraft.

Scope of engagement:
  • Review of GKN own Health & Safety documentation
  • Provision of Comprehensive Construction Phase Health & Safety Plan for the works
  • Bi lingual Health & Safety site rules and induction
  • Proactively working with UK and German subcontractors to ensure documentation in place and that safe systems of work maintained on site
  • Provision of full time on site Health & Safety management support for the works
  • Provision of full time gateman to ensure CDM control of persons / vehicles on site
Mechanical Test Facility Transition

For Scholpp GmbH, Constructus provided the complete Health & Safety management for Scholpp as the Principal Contractor for the removal and packing of a complete materials test facility for Rolls Royce Aerospace as part of their MTOC (Mechanical Test Operations Centre) which required transition to Germany of the majority of the Derby based material test operation.

Scope of duties:
  • Review of RR own documentation
  • Provision of Comprehensive Construction Phase Health & Safety Plan for the works
  • Proactively working with UK and German subcontractors to ensure documentation in place and that safe systems of work maintained on site
  • Provision of visiting Health & Safety management support for the works
Planar Biaxial Engine Blade Test Machine Installation

For MTS Systems, Constructus provided the Project and Health & Safety management for the installation of four Planar Biaxial, Environmental test machines at Rolls Royce Derby.

Scope of work:

  • Preparation of Health & Safety documentation
  • Liaison with Rolls Royce project manager
  • Management of MTS specialist lifting contractors
  • Supervision of works on site
  • Direct assistance to MTS field service Engineers
Aerospace Test Facility Installation

For MTS Systems, Constructus provided the project management for the installation of 12 aerospace materials load frames and coordination with clients own contractors at Exova Lancaster.

Scope of works:
  • Preplanning
  • Preparation of Health & Safety Documentation
  • Liaison with Exova and MTS project staff
  • Management of MTS specialist lifting contractors
  • Laision with Exova directly employed subcontractors
  • Supervision of works on site
  • Direct assistance to MTS field service Engineers
Loadframe Upgrade

For MTS Systems, Constructus provided Health & Safety consultancy for the modification of load testing machines at Siemens Gas Turbines

Scope of works:
  • Review of machines on site & technical drawings
  • Review of Siemens own safety requirements
  • Writing suitable work methods & assessment of risks for site works
 
 
 
 
 